1.200mm half round PVC gutter with down pipes@10.14m intervals
2.alum window top hang with Georgian bar(see win schedule)
3.Cladding (sheets) screwed to sheet rail bolted to cleats weilded to columns(to detail)
4.roofing sheets onto sissalation onto angle purlins bolted purlin cleats weilded to spaning member
5.ridge ventulator to detail
6.universal beams main beams(connection to Eng detaul)
7.Suspended floor slab to be given steel trowel finish(To Eng.detail)
8.Secobndary beams(Connection-to Eng.spec)
9.Internal pressed steel stairs (to eng.detail)
10.transparent cladding
11.150m solid blockwork to be plastered both side and apply 3 coats of emulsion paint
12.1RC floor slab to eng.detail
13.stand alone Hoist Lift lift pit to be optional
14.Universal beams main beam(connection to Eng detaul)
15.RC Ramp To eng.detail
还有几个:sercice balcony,light storage,slidding door,vertical slidding window