英语翻译A project scheduled to be carried out over a single fiscal year has a budget of 12600,divided into 12 equal monthly allocations.At the end of the fourth month of that fiscal year,the total amount actually spent on the project was 4580.By how much was the project over its budget?
问题描述:
英语翻译
A project scheduled to be carried out over a single fiscal year has a budget of 12600,divided into 12 equal monthly allocations.At the end of the fourth month of that fiscal year,the total amount actually spent on the project was 4580.By how much was the project over its budget?
答
一个预算计划表,算出来一个财政年的预算是12600,均分到12个月.截至这个财政年的第四个月末,总共项目花销是4580,请问到第四个月末的时候,超出了预算多少?
12600/12=1050 1050*4=4200 4580-4200=380
答:超出预算380