英文合同部分内容求翻译Contractor commits to finish the manufacturing of the tool(milestone 1) according to the updated time schedule 27.09.2007 at latest. The invoice of the Contractor takes to consideration the payment made to the Subcontractor. All other provisions as agreed between REHAU and the Contractor as well as the Contractor and the subcontractor remain unaffected. Constractor is already behind the delivery schedule as agreed in pur purchase order5/270
问题描述:
英文合同部分内容求翻译
Contractor commits to finish the manufacturing of the tool(milestone 1) according to the updated time schedule 27.09.2007 at latest.
The invoice of the Contractor takes to consideration the payment made to the Subcontractor.
All other provisions as agreed between REHAU and the Contractor as well as the Contractor and the subcontractor remain unaffected.
Constractor is already behind the delivery schedule as agreed in pur purchase order5/2704 dated 19.04.2007
答
合同者履行完成工具(英里石头 1)包括其升级(或者更新)具体时间不可迟于27.09.2007
关于付款清单由亚合同者提供
答
英里石头?是里程碑。
答
承包人承诺根据更新的时间表,最迟在2007年9月27日完成工具的制造(里程碑1).
承包人的发票需考虑到给分包人的酬劳.
所有其它的条款由REHAU和承包人之间达成协议,且承包人和分包人不会受到影响.
根据2007年4月19日协定的购销合同5/2704规定的交货日程表,承包人延期了.